Nearly here for the basic building. Concrete pump arrived at dawn on Wednesday, unfortunately the concrete didn’t until 9am. Unfortunately the camera batteries didn’t like working at that time or perhaps it was just the cold. Still the floor and the front apron is now complete. Work continues on the gables but the ridge tiles have been completed. All the drains are connected to the soakaway and the tiles along the valley gutter need trimming-back. Hopefully complete by the end of week 12. Of course our week will still need completing; painting the walls, electrics, lighting, water/sink, the inlaid track in the floor, door cladding and probably much more I have forgotten.