Workshop Progress – Week 2

Second week finished and only 1 day of rain.

Progress has been rapid. Soakaway dug and piped, blockwork to slab level laid, and some brickwork rising. Am on holiday for a week so not sure when the next update will be. Photos attached.

Alan Hooper

 

DSCN1754 DSCN1777 DSCN1778 DSCN1779 DSCN1780 DSCN1781 DSCN1785

Leave a Reply