Work started on-site on 2nd September and due to the good weather has progressed rapidly in the first week. The site has been cleared, foundations dug, checked by the building inspector and filled with concrete. One set back has been that the original soakaway is under the proposed building, requiring more excavation and longer pipework. A selection of photos will hopefully be attached.
Alan Hooper
Fantastic progress!