Go away for a week and you certainly notice the progress. The steel frames for the doors have been made and delivered by Tim Hims, and the trusses delivered by the supplier.
Some photos attached for work up to Friday 27th. September.
Work started on-site on 2nd September and due to the good weather has progressed rapidly in the first week. The site has been cleared, foundations dug, checked by the building inspector and filled with concrete. One set back has been that the original soakaway is under the proposed building, requiring more excavation and longer pipework. A selection of photos will hopefully be attached.
Alan Hooper
The Committee has called for an EGM for 7:30pm Wednesday 31st. July 2013 at Ashton Court Railway for the approval of the Workshop/Maintenance Facility.
Alan Hooper
Secretary